The new Tacloban Airport terminal building is set to partially open by 2026, with the long-term goal of meeting international standards by 2028, officials announced on Wednesday.
Construction is progressing across three phases of the project, following intensified monitoring and problem-solving sessions initiated by the Regional Development Council (RDC), according to Department of Economy, Planning, and Development (DEPDev) Regional Director Meylene Rosales.
“Contractors have been true to their promise to fast-track the project,” said Rosales, noting that the RDC Regional Project Monitoring Committee and the Office of House Speaker Martin Romualdez have been closely involved.
Phase 1 of the project, which includes the construction of the new passenger terminal building, is nearly completed, with PHP761.91 million worth of work finished. The second phase, which has a PHP1.05 billion budget, is set for completion in early 2026. Ongoing work includes roofing and architectural construction.
Phase 3, with an estimated cost of PHP1.5 billion, will complete the terminal and other airport facilities. The Department of Public Works and Highways (DPWH) is overseeing this phase, which includes the installation of elevators, escalators, air-conditioning systems, and passenger boarding bridges. The terminal is expected to open for domestic flights in 2026.
The Tacloban Airport is one of the busiest in the country, serving 1.69 million passengers in 2024 with 24 daily flights between Manila and Cebu. The airport, named after former Speaker of the House Daniel Z. Romualdez, is a key gateway to Eastern Visayas and is expected to become an international hub by 2028.