TACLOBAN CITY – The Department of Public Works and Highways (DPWH) in Eastern Visayas is accelerating construction of the Php 4.4-billion Tacloban-Palo Diversion Road, also known as the “Grand Canal,” despite receiving no additional funding under its 2026 budget.
In an update on Tuesday, November 17, DPWH-8 reported that 756 meters of the road and drainage system had been completed, while another 1.25 kilometers remained under construction as of the end of October.
The ongoing construction is being financed through the agency’s 2024 and 2025 appropriations, while previously completed sections were funded under the 2019, 2023 and 2024 national budgets.
DPWH Eastern Visayas Regional Director Edgar Tabacon expressed hope that additional funding would be approved to ensure the project’s completion.
“While funding approval is not within our control, we hope that future funding will be approved and included in the national budget. The completion of this project will have a significant impact on our communities,” Tabacon said.
According to DPWH-8, approximately Php 2.33 billion had been released for the project as of 2025, while the remaining Php 2.1 billion has been proposed for inclusion in the 2027 national budget.
The additional allocation is intended to complete the 3.23-kilometer road and drainage system connecting Tacloban City and Palo, Leyte.
Major flood control project
The Grand Canal project involves the construction of a four-lane highway stretching from the San Jose district in Tacloban City to Barangay Campetic in Palo.
A major component is a 16- to 22-meter-wide drainage and flood control channel positioned along the center of the roadway.
The design aims to improve water flow, prevent obstruction of drainage channels and reduce flooding in surrounding communities.
Once completed, the system is expected to help address recurring flooding in Barangays Candahug, Pawing and Campetic in Palo, as well as Caibaan, San Jose, Marasbaras and Manlurip in Tacloban City.
Residential areas such as V&G Subdivision and Imelda Village are also expected to benefit from the improved drainage infrastructure.
These communities have experienced prolonged flooding during heavy rainfall and typhoons, with floodwaters sometimes taking weeks to subside.
Aside from flood mitigation, the diversion road is designed to improve transportation connectivity between Tacloban and Palo.
The project will include bicycle lanes, sidewalks, service roads, solar-powered streetlights and road safety facilities.
DPWH expects the infrastructure development to improve accessibility and help transform previously idle and flood-prone properties into areas suitable for commercial and economic activities.
However, the project’s full completion remains dependent on the approval and release of additional government funding.