The Commission on Audit (COA) has ordered a fraud audit of flood control projects in Bulacan, which was recently hit by severe flooding. The move seeks accountability for failed projects across the country.
In a memorandum issued by COA chairperson Gamaliel Cordoba, supervising auditors and audit team leaders of the Department of Public Works and Highways (DPWH) District Offices in Region 3 were directed to submit all necessary documents and ensure their availability to assist audit teams.
“Given the critical issues raised by President Ferdinand R. Marcos Jr. regarding the implementation of these projects, particularly in the Province in Bulacan, a fraud audit is an immediate and unequivocal necessity,” COA stated in the memo dated August 12.
The order covers DPWH’s flood control projects in Bulacan, which received P44 billion—the largest allocation in Region 3, accounting for 45% of the region’s flood control budget.