Aboitiz Renewables Inc. is optimistic about its energy transition plans after its subsidiary, AP Renewable Energy Corporation, secured a PHP7.4-billion loan from Bank of the Philippine Islands for the 221-megawatt peak (MWp) Olongapo solar power plant in Zambales.
The project, which began construction in early 2024, is now 95 percent complete and is expected to undergo testing and commissioning by the third quarter of 2025, connecting to the Castillejos 230-kilovolt substation.
“Olongapo Solar represents a major contribution to AboitizPower’s clean energy portfolio and more so to achieving the Philippines’ energy transition targets,” Aboitiz Renewables President Jimmy Villaroman said.
He added, “Every project we build is the product of a highly motivated organization contributing to Aboitiz Power’s energy transition effort.” Once operational, the plant will be the company’s largest solar project to date.