SC upholds order fast-tracking energy projects

The Supreme Court (SC) has upheld Executive Order (EO) No. 30, a 2017 directive from Malacañang aimed at expediting the approval of energy projects of national significance (EPNS).

In a decision released Tuesday, the SC en banc dismissed a petition filed by citizen groups seeking to block the implementation of the order through an Environmental Protection Order.

EO 30 lays out streamlined guidelines for processing EPNS applications. These include simultaneous permit processing even if other approvals are still pending, a 30-day deadline to act on complete applications, and automatic approval if agencies fail to act within the deadline.

Petitioners argued that EO 30 oversteps the President’s authority, undermines environmental safeguards, and imposes unrealistic timelines on complex energy projects that often take years to complete.

The SC rejected these claims, saying the President is allowed to simplify government procedures as long as they remain consistent with existing laws. It added that EO 30 aligns with the goals of the Electric Power Industry Reform Act of 2001 and the Department of Energy Act of 1992.

The Court clarified that the order sets minimum standards for agencies to follow and allows flexibility to meet legal and environmental requirements.

“The presumption of prior approval means permits can be processed at the same time, not skipped altogether,” the SC said. “The 30-day timeframe is even more flexible than deadlines under other laws like the DOE Act and the Ease of Doing Business Act, which also adopted automatic approval mechanisms.”