Not all flood control projects are anomalous Australia-based firm 

A person with short black hair and glasses, smiling at the camera while wearing a dark green polo shirt with the logo of 'Artea Green Ventures' in an outdoor setting.

Artea founder and master environment auditor Annabelle Tungol. (Photo from GoFundMe)

NAUJAN, Oriental Mindoro — Based on its independent audit, an Australia-based consultancy firm has dispelled doubts of ‘ghost’ or substandard infrastructure projects in the province as it confirmed the existence of six flood control projects that “are real, on-site, and in various stages of completion.”
According to Artea Green Ventures, it has conducted an inspection and monitoring of the mentioned projects and they have not found anything suspicious in their implementation, although the contractor was not named.
Artea’s master environment auditor and licensed chemical engineer Annabelle Tungol noted that “after going to the project sites, we confirm that the six projects (. . .) have been audited and found not guilty.” She, however, pointed out some area for reform could be done.
An Australian government website describes Artea Green Ventures as “an environmental consultancy delivering compliance auditing, independent audit, ESG advisory and sustainable infrastructure solutions across Australia and Philippines,” that partners with “Movementsoft Inc, a trusted ICT provider currently serving the Department of Public Works and Highways (DPWH)” for its work in the Philippines.
Tungol and four other auditors inspected six dikes and esplanades alleged to be ghost projects in Naujan.
Artea’s audit report stated that the project generally complied with design standards, where erosion protection and solar-powered light poles are present. In addition, there is also active supervision and community consultations bei g conducted.
Despite these findings, the independent audit pointed out localized issues such as exposed rebars, concrete cracks, and poor waste disposal were observed, which is mostly tied to a single contractor.
“While ghost project allegations were proven false, systemic reforms are still needed to ensure the long-term integrity of flood control infrastructure,” the report likewise disclosed even as it recommended the implementation of stricter contractor evaluation, mandatory safety training for site workers and regular independent audits to strengthen transparency and public trust.