NEA aims for 24/7 power restoration in Siquijor by Sunday

The National Electrification Administration (NEA) is targeting the restoration of 24/7 power in the province of Siquijor by Sunday, with the anticipated arrival of generator sets (gensets) supplying 4 megawatts of power.

NEA administrator Antonio Mariano Almeda announced that the gensets are scheduled to arrive in Dumaguete on Friday noon and will be transported to Siquijor the same day. “24-hour power should be online by Sunday,” he stated in a radio interview with DZMM.

President Ferdinand Marcos Jr. previously directed the Department of Energy, the NEA, and the Energy Regulatory Commission to address the power crisis in Siquijor, which has been facing 20-hour blackouts due to insufficient power supply. Almeda noted that the province is currently experiencing 5-hour rotating blackouts daily.

Energy Secretary Sharon Garin indicated that Siquijor Island Power Corp. (Sipcor), the sole power supplier on the island, can only deliver 5-6 megawatts of power, while the demand ranges from 8-9 megawatts.

To assess the situation, Almeda mentioned that a team of engineers from the University of the Philippines is set to conduct an independent audit of the Sipcor plant to determine its viability in supplying electricity to the island.

“We have to determine kung kakayanin ng Sipcor to serve the people of Siquijor. We have some plans already on a possible takeover,” he added, indicating that alternative solutions may be explored to ensure a stable power supply for the residents of Siquijor.Bookmark messageCopy messageExport