Japanese firms ask extension in bidding for Philippines longest railway

Modern red and silver commuter train on railway tracks under a blue sky

By Tracy Cabrera

Two Japanese companies have shown keen interest in the project to build the country’s longest railway as they requested for an extension in the bid deadline for the private turnover on the North-South Commuter Railway (NSCR).

According to Department of Transportation (DoTr) secretary Vivencio ‘Vince’ Dizon, Tokyo Metro Company Limited and East Japan Railway Company have both expressed their desire to join the bidding process for the NSCR.
Dizon said they have granted the request, pushing the bid submission deadline to January 2027, from the original schedule of May 2026.

In market sounding activities, the DOTr has been courting the interest of Japanese railway giants. Tokyo Metro runs Asia’s first subway while East Japan Railway manages the bullet train Shinkansen.

The NSCR, costing ₱873.6 billion and co-funded by the Japanese government, will span 147 kilometers between Clark International Airport and Calamba, Laguna, creating the country’s longest railway.

It will be built with 35 stations across Central Luzon, Metro Manila and Southern Tagalog and will also establish the country’s first airport express.

Based on updated timelines, the NSCR will open its partial operations between Valenzuela and Malolos by the end of next year and will run fully only by 2032.

The winning operator of the NSCR is expected to spend as much as ₱229.3 billion to operate and maintain the project. The concessionaire will handle the railway for 15 years, on top of 7.5 years for partial operations.