By Lizbeth Ann Abella
TACLOBAN CITY – The Department of Public Works and Highways (DPWH) Eastern Visayas has assured corrective works on the ongoing Gandara 2 Parallel Bridge project in Samar after the collapse of its two girders.
DPWH Eastern Visayas Regional Director Edgar Tabacon said in a statement on Friday that they had inspected the bridge to check its condition, removed the debris, and carried out safety measures while construction continues.
“The DPWH has initiated clearing operations at the affected portion while installation works for additional girders are underway to avoid further delays in the project,” the official stated.
Based on the department’s initial technical assessment, the collapse was not attributed to the use of substandard construction materials. The DPWH also assured the public that the bridge’s piers and abutments remain stable.
Public Works Secretary Giovanni Lopez earlier ordered the mobilization of a technical team to assess the incident and determine the necessary corrective measures.
Lopez also checked the project Friday afternoon.
President Ferdinand Marcos Jr. likewise directed the department to ensure the safety of construction workers and motorists, including those using nearby roads and bridges.
Tabacon said the project contractor has accepted responsibility for the incident and assured the government that replacement of the damaged girders would be undertaken at no additional cost to public funds.
The project, titled Widening of Permanent Bridges: Gandara 2 Parallel Bridge along Gandara Diversion Road, involves the construction of a 70-linear-meter bridge under Phase 1, with a project cost of PHP92.61million.
The bridge is intended to provide wider lanes and safer passage for motorists and pedestrians, accommodate increasing traffic volume and larger vehicles, and improve travel efficiency and reliability for the public. (PNA)