MANILA – The Department of Public Works and Highways (DPWH) temporarily removed barriers along the northbound sections of EDSA near the Kamuning and Nepa Q-Mart stations in Quezon City ahead of concrete reblocking activities under Phase 2 of the EDSA Rehabilitation Project beginning Friday evening.
DPWH Secretary Banoy Lopez said the removal was in compliance with President Ferdinand Marcos Jr.’s directive to ensure motorists’ safety and prevent accidents in areas undergoing road rehabilitation.
The barriers will be reinstated once concrete reblocking and asphalt overlay works in the affected sections are completed.
Despite the temporary removal, the DPWH stressed that private vehicles remain prohibited from entering the EDSA Busway. Motorists were reminded to strictly observe traffic signs and on-site advisories.
The three-day rehabilitation works will cover selected sections along the following areas:
- Southbound: EDSA near Apo Street in Guadalupe, Makati City, to EDSA Boni Avenue near Lions Road in Mandaluyong City.
- Northbound: Santolan Bus Station to Quezon Avenue Bus Station in Quezon City.
Construction activities will begin at 10 p.m. on November 27, involving pavement breaking and debris hauling.
Round-the-clock operations will continue on November 28 and 29, covering base preparation, installation of reinforcing steel bars, concrete pouring, pavement cutting, sealant application, curing, and site clearing.
Temporary lane closures will be implemented in affected sections throughout the rehabilitation period, while the remaining lanes will stay open to vehicular traffic.
The DPWH advised motorists to exercise caution, comply with traffic management measures, and consider alternative routes to minimize travel disruptions.
All affected road sections are scheduled to reopen to traffic at 5 a.m. on Monday, November 30.