Fifteen power generation companies have formally entered the Competitive Selection Process (CSP) for Manila Electric Company’s 200-megawatt renewable energy baseload requirement, signaling strong market interest in supplying clean and reliable power to the country’s largest distribution utility.
The prospective bidders, which earlier submitted Expressions of Interest, took part in the pre-bid conference on January 15 ahead of the formal submission of offers next month. The participating firms are ACEN Corporation, AP Renewable Energy Corporation, Bac-Man Geothermal Inc., Energy Development Corporation, First Gen Hydro Power Corporation, GNPower Kauswagan Ltd. Co., GNPower Mariveles Energy Center Ltd. Co., Green Core Geothermal Inc., Mariveles Power Generation Corporation, Negros Island Solar Power Inc., SanMar Solar Inc., Sinocalan Solar Power Corporation, Sual Power Inc., Therma Luzon Inc., and Therma Visayas Inc..
Meralco Bids and Awards Committee chairman Lawrence S. Fernandez said the broad participation underscores confidence in the CSP framework.
He noted that the process remains an effective tool for securing sufficient and least-cost power supply for consumers, adding that the utility is looking forward to receiving competitive offers on the bid submission deadline set for February 16.
The Power Supply Agreement to be awarded from this CSP will cover Meralco’s 200-MW renewable energy baseload requirement to meet Renewable Portfolio Standards compliance beginning January 26, 2026, subject to approval by the Energy Regulatory Commission.
Meralco said the bidding exercise is aligned with its annual Power Supply Procurement Plan approved by the Department of Energy, and reiterated its commitment to conducting open, transparent, and competitive CSPs in full compliance with government rules and regulations.