top of page
Khomfie Manalo

Admin sync initiatives for 1st offshore wind project in 2028

The Marcos government is synchronizing its plans to fast-track the development of offshore wind energy projects and ensure that the first one is operational before the administration ends its term in June 2028.


In a memorandum of agreement, the Department of Energy (DOE) and the Department of Environment and Natural Resources (DENR) pledged to allow offshore wind energy developers with service contracts to access offshore and auxiliary areas during the pre-development phase of their projects.


"This MOA is a crucial step in realizing the goal of the administration of President Ferdinand Marcos Jr. to deliver the first kilowatt-hours from offshore wind projects by 2028," Department of Energy (DOE) secretary Raphael Lotilla said in a statement.

 

Renewable energy (RE) projects are required to secure various compliance certificates from DENR, such as foreshore lease agreements, forest land use agreements, and miscellaneous lease agreements, before proceeding with exploration and development.

 

"By streamlining the process for accessing critical areas, we are paving the way for a rapid and responsible rollout of offshore wind projects, which will contribute significantly to our clean energy transition," the energy chief added.

 

Despite expediting the process of giving access to the areas, the MOA will continue to ensure that environmental safeguards are upheld at every stage.

 

During the Renewable Energy Forum organized by the Economic Journalists Association of the Philippines and Aboitiz Power Corp. on the same day and venue of the MOA signing, Lotilla said RE stakeholders should expect more streamlining of processes to accelerate the development of RE projects.

 

Lotilla said he met with President Ferdinand R. Marcos Jr. last week and discussed possible solutions to address the slower system of permitting process in RE projects versus conventional energy projects.

 

He said the permitting process accounts for the significant delays in building RE facilities.

 

"We will not pursue successive permitting or sequential processing, which accounts for the delay. We will pursue parallel processing to the fullest extent possible. That means they expect that several agencies can proceed with their permitting processes without having to await the decision of other agencies," he said. 

17 views0 comments

Comments


bottom of page